Asheville's temporary outdoor skating rink at 50 Asheland Avenue is paved and fenced and due to open in early 2027. It is meant to stay up to five years.
Asheville’s temporary outdoor skating rink is taking shape in a city parking lot at 50 Asheland Avenue downtown. The city expects it to open in early 2027, and possibly sooner.
Asheville Parks and Recreation posted the progress on the project’s public page. Site grading and paving are done. The retaining wall, curbs, fencing and parking spaces are in.
What is still to come
In the coming weeks, the city said, it will add:
- tree plantings and other landscaping
- trash cans, signs and site furniture
- the rink itself
Duke Energy will add more lighting for safety, the project page said.
The rink is for recreational skating and inline hockey, according to the city’s project overview.
Why a temporary rink
Tropical Storm Helene left Asheville without a public skating rink, the city said. That cut off family skate sessions, youth hockey and recreation programs.
“This project provides a temporary home for those activities while long-term recovery at Carrier Park moves forward,” Asheville Parks and Recreation Director D. Tyrell McGirt said in June.
A permanent public rink is planned at Carrier Park as part of the French Broad Riverfront Parks Recovery project. The Asheland Avenue rink is expected to stay open for up to five years, until the permanent one is finished.
How it was paid for
City Council approved a contract to prepare the site on June 23. The resolution also moved existing federal grant money to cover part of the work, according to the city’s summary of that meeting.
On Sept. 8, council moved $105,000 in donated funds to buy materials for the rink, the city’s September meeting summary said.
What happens to the lot later
The rink is a stopgap. The city plans to use the Asheland Avenue site later for housing and services for residents and transit riders, as part of its ART Place project.
What it means for you
- No opening date or skate hours have been set. The city’s target is early 2027.
- Expect landscaping and lighting crews at 50 Asheland Avenue over the next few weeks.
- Questions go to project manager Al Kopf at Asheville Parks and Recreation, 828-259-5800.