Buncombe County is designing its first indoor recreation center, with basketball and volleyball courts, at Buncombe County Sports Park. The public can see the plans Dec. 8.
Buncombe County is designing its first indoor recreation center. It would have basketball and volleyball courts and double as an emergency shelter after a disaster.
The building is planned for Buncombe County Sports Park, about five miles west of downtown Asheville. The county will show residents the project at a drop-in session from 5 to 7 p.m. Tuesday, Dec. 8, at Sand Hill-Venable Elementary School.
The county announced the session Friday in a news release.
What the county wants to build
The facility would sit on what is now Field 9, in the upper section of the park. That is county land, so no purchase is needed, according to the county’s project page.
The proposed amenities listed on the county’s public input page include:
- basketball and volleyball courts
- locker rooms and a kitchen
- multipurpose rooms for community events, which could also serve as polling places
- conference rooms
- offices for Buncombe County Parks and Recreation
- a new entrance and exit for the park
The county said the building will be designed to handle emergency response and sheltering if needed. It picked the upper field partly because the site “will likely remain accessible during a major weather event.”
A second site, the former General Services grounds facility in the lower part of the park, was considered and passed over. The county said that area is more likely to be cut off by flooding and would leave too little room for parking.
What it could cost
Commissioners approved a $1,599,220 design contract with architecture firm Method Studio on Aug. 18, according to the board’s resolution.
Method Studio’s fee proposal, attached to the contract, puts numbers on the early plan:
- about 28,000 square feet of building
- construction estimated at about $535 a square foot, or $15 million
- another $1.75 million to $2 million for rooftop solar panels and battery storage, enough to run the building for one day before generators take over
The firm said the size will be checked during the first design phase. The county said the project will be paid for with grants and money from its FY27 capital improvement plan.
When it could open
The building is years away. The project team held its kickoff meeting at the end of September. The county expects the design phase to be finished in fall 2027. That phase covers concept design, budget alignment, construction documents and permits.
After that, commissioners would need to approve a construction contract. The county expects construction to take 16 to 18 months.
| Step | Status |
|---|---|
| Design contract approved | Aug. 18, 2026 |
| Project kickoff | End of September 2026 |
| Public information session | Tuesday, Dec. 8, 5 to 7 p.m. |
| Design and permits finished | Fall 2027 (county estimate) |
| Construction | 16 to 18 months after a contract is approved |
What happens to the dog park and the garden
The park is home to Sand Hill Community Garden, a tree nursery run by Asheville GreenWorks and a dog park. The county said no design has been finalized, so it does not yet know whether any of them will be affected.
If they are, the county said it will work with the groups that run them to move them. A slide shown to commissioners in August said the chosen site “will preserve some of the existing amenities at the dog park and community garden.”
Neighbors may see surveyors on the site in the coming months, the county said.
What it means for you
- See the plans: drop in any time from 5 to 7 p.m. Tuesday, Dec. 8, at the Sand Hill-Venable Elementary School library, 154 Sand Hill School Road. County Parks and Recreation and General Services staff and the Method Studio team will answer questions.
- Follow the project: subscribe for updates on the county’s Indoor Recreation Facility Project page. The county said residents will get to review and comment on design concepts later.
- Using the park now: nothing changes yet. The fields, garden and dog park stay open while the design work goes on.
For other things to do around town this month, see our things to do page.